Mongolia premier pledges to end Tavan Tolgoi coal mine & railroad delays

From the Financial Times news report comes this upbeat news from Mongolia.

The headline:

Is this just more public relations political hype? Another “junk” rated bond issue to please voters? Is this necessary? Probably a bad idea. Again.

More long delayed plans for the east-west low margin financial feasibility railroad towards Japan? These sound more like a belief in Santa Clause than a sound strategic recovery for the nation.

I would wish more then this for my many Mongolian friends I have worked with.

The good news is that there is a way to make Mongolians strategic winners” if they pull together on tactics and engineering that are sound best practices.

Cheers!

For the FT report, log onto: http://www.ft.com/intl/cms/s/6e7a241a-20c7-11e5-ab0f-6bb9974f25d0,Authorised=false.html?_i_location=http%3A%2F%2Fwww.ft.com%2Fcms%2Fs%2F0%2F6e7a241a-20c7-11e5-ab0f-6bb9974f25d0.html%3Fsiteedition%3Dintl&siteedition=intl&_i_referer=#axzz3erCpC6bE

Here are a few of the reported public relations statements in the news report. ——- Saikhanbileg Chimed indicated that “Mongolia planned to launch another sovereign bond as the country seeks to get “back to business” following two years of slowing growth in gross domestic product, plummeting foreign direct investment and rating agency downgrades of its junk-rated “Chinggis” bonds.”

“Official approval for investors to start work on the Tavan Tolgoi (TT) coking coal mine in the Gobi desert should follow soon after a review of the investor agreement in parliament this month, Mr Saikhanbileg told the Financial Times in an interview.”

Investors in the project include China’s Shenhua Energy and Japan’s Sumitomo Corp. “TT will be unlocked in the very near future,” he said.

HOWEVER—

“Several members of Mongolia’s parliament have raised objections to financial and legal aspects of the TT investor agreement, raising the possibility that the mine… …could suffer a similar fate to that of Oyu Tolgoi, a $5bn copper mine, where an expansion project was unblocked in May only after two years of wrangling. This year, Mongolia resorted to a mobile phone referendum to shore up public support for the project…

The minister still believes in 220km rail line from the mine into China — delayed now for more than three years.

Mr Saikhanbileg also told the FT reporters that he also believes in a second potential rail project that would run east-west about 1,300km to reach coal markets in Japan and the US, a Mr Saikhanbileg said.

BEWARE:

This E-W rail line is a much higher investment risk according to my due diligence research on Mongolia rail options dating back to 2006.

Investors need to carefully reexamine these projects with updated due diligence.  Mongolia needs a real heavy haul big train design to make their expectations a reality.  That means trashing most of their prior rail designs.

It also means a fresh due diligence review of the feasibility options. In particular, it is a bad idea to depend upon a due diligence feasibility report that is prepared by the builders.  They are not exactly Independant.